Gihogwe Secondary School

The project so far (in reverse chronological order):

Shown here is an artists impression of the new dormitory/classroom/shower block which has just begun - the photos show progress to January 2012.

Completion of the new block is entirely dependent on sufficient funding being raised.
New dormitory block - artists impressionGirls dormitory January 2012
Water harvesting project
Photo on left is of the water harvesting project at the secondary school showing
 progress as at September 2011, work continues on this project until completion.
Girls dorm July 2011
PlaygroundBoys temporary accommodation
Boys toilet block under construction

Playground complete but waiting for us to be able to buy netball posts - July 2011

Temporary accommodation for boy boarders - March 2011Boys toilets are now urgently needed and must be finished asap as Rwandan government is pressuring us - March 2011
Gihogwe students

Some of the students
Mosquito nets benig used in Gihogwe School dormitory

Mosquito nets in the dormitory
Students playing volleyball

Some of the students playing volleyball
The kitchen
The kitchen with the cooking and 
washing up station being built - Feb 2010
The completed security hut
The security hut is now complete -
Feb 2010
The start of the new dormitory/classroom/shower block
The beginnings of the new dormitory/classroom/shower block -
Feb 2010
A completed classroom

The school's headmaster Claude Bigabbo in the library
Interior of the dining room

Photo of completed dining room  - February 2010







Pictured alongside are some of the children now receiving an education at the school
Completed dining room
Completed dining room
Making desks
'Janvier' making desks for the classrooms
School library
The school library

The 2 classroom blocks
The two classroom blocks - Nov '09
Land cleared for playground and next dorm block
Land cleared ready for playground and next dormitory block

Right - completed dining room and kitchen
Completed dining room/kitchen


Toilets and showers
Toilets and showers
Security hut under construction
Security hut under construction

Dormitory room
Dormitory room
School fence
School boundary fence


The toilet and shower block were started in June 2007, and the dining room was started in October 2008.

Toilet & shower block
Toilet & shower block
Dining room site
Dining room site

Gihogwe classroom block

The first building constructed was a block of classrooms and offices and the school was
opened in February 2008 with 43 day students.








The dormitory block was the next building to be
finished and this has places for 92 students.
In Rwanda it is important that such accommodation is provided as many children do not live in conditions
 that are conducive to studying. The dormitory block was completed in December 2008
Dormitory block
Dormitory block completed

Dormitory block under construction
Dormitory block under construction




Where it all starte
d!!

Land for Gihogwe secondary school




The project to build Gihogwe secondary school commenced in 2005 when the land was purchased and planning permission for the school was obtained